Relevant Project Features:

  • Performed additional site investigation
  • Prepared Final Addendum to Site Investigation Report
  • PerformedĀ  Passive Remediation
  • Prepared Remedial Action Work Plan
  • Coordinated with RIDEM

RT Group, Inc. (RTG) was retained by the Capital Terminal Company to amend/update the Site Investigation Report (SIR) prepared by others, and prepare the Remedial Action Work Plan (RAWP) for addressing a 3,000-gallon diesel fuel release that occurred in 1994.

CTC 2Following the above work, RTG was retained to design the active remediation system that includes the installation of product recovery pumps (Phase I) and the possible installation of groundwater recovery pumps to address dissolved phase contamination (Phase II).

Work on this remediation project is ongoing and is expected to take about one (1) to two (2) years. RTG has been retained to install, operate, and maintain the remediation system during this time.